Introduction
Transmission system operators (TSOs)
throughout the world have been seeing growing numbers of transmission line
projects in recent years for different reasons including the increase of
cross-border trade, renewable energy sources, smart grid projects, the
replacement of aging facilities, and in some countries due to growing demand.
Until recently, TSOs have
responded to these necessary transmission upgrades mostly by the introduction
of overhead lines (OHLs). HVAC underground cable systems have been used, but
their applications have been mainly limited to densely populated areas. As
such, HVAC underground cable systems are limited both in length and number to
date.
This tendency has been changing
over the past 10 years as the service experience of HVAC, especially EHV AC,
cable systems has become satisfactory. The applications of HVAC cable systems
are proposed more often in order to protect the landscape and also public
health (e.g., EMF). Hence, HVAC cable systems recently planned or installed are
longer than those installed previously.
For example, in Denmark, after
receiving public and political pressures to underground its OHLs, Danish TSO,
Energinet.dk, published a report on the future expansion and undergrounding of
its transmission grid on the 3rd of April 2008. The report proposed and
compared five principles (A–E in Figure 1.1). From the five principles, the
Danish government has selected Principle C, as shown in Figure 1.2, in which
all new 400 kV lines will basically be undergrounded.
A similar tendency can be
observed on HVDC, especially EHV DC, submarine cable systems. The Nor Ned
cable, which connects Norway and the Netherlands, and the Brit Ned cable, which
connects the Netherlands and the UK, are symbolic examples of such a trend.
These cable lines, mainly for cross-border trades, have a total length of 580
and 260 km, respectively.
Five principles for the future
grid expansion
|
The scale of these projects is
beyond the level many people expected at the beginning of this century.
As these cable projects increase, there is an increased need to study cable system transients. In particular, the introduction of long cable systems may cause peculiar phenomena, such as resonance over voltages, which require careful attention. Severe temporary over voltages in the power system with long cable systems which can be caused in specific network conditions or configurations have been reported.
As these cable projects increase, there is an increased need to study cable system transients. In particular, the introduction of long cable systems may cause peculiar phenomena, such as resonance over voltages, which require careful attention. Severe temporary over voltages in the power system with long cable systems which can be caused in specific network conditions or configurations have been reported.
Cable modeling for studies on
cable system transients, as discussed in Chapter 4, requires the understanding
of cable systems. This chapter first discusses the cable itself and then
introduces the laying configuration and the sheath bonding, that is, the cable
as the cable system. Various cables used in practice are explained in the
following two sections – land cables in Section “Land Cables” and submarine cables in Section “Submarine Cables”. Section “Laying
Configurations” discusses the laying configuration including the sheath
bonding. The main focus of this chapter is on how these physical
characteristics of cable systems affect their electrical characteristics.
Land cables in Section “Land Cables” cover three major cable
types, that is, XLPE (cross-linked polyethylene, PE) cables, SCOF/SCFF (self-contained
oil-filled/self-contained fluid-filled) cables and HPOF/HPFF (high-pressure
oil-filled/high-pressure fluid-filled) cables. The term “fluid-filled” is used
to include both oil-filled cables and gas-filled cables, but most fluid-filled
cables are oil-filled cables in actual installations. Even though XLPE cables
are increasingly selected for new cable lines in many countries, SCOF cables
and HPOF cables are still a popular choice in some countries. HPOF cables are
selected, in particular, for the replacement of old HPOF cables since it is
often possible to continue using their steel pipes even after the cable
replacement.
The laying configuration and the
sheath bonding affect cable system transients as the cable itself does. They
need to be modeled correctly in order to obtain accurate impedance/admittance
of the cable system or reasonable simulation results. Section 1.4 discusses
different laying conditions and sheath bonding methods together with their
impact on the cable system transients.
Grid expansion plan based on Principle C |
For rest of the details of this topic please visit the hyperlink in the post or visit suggested posts below this post.
No comments